Previous Dry Dock
October 21, 2024 - November 11, 2024
Norwegian Star underwent an extensive technical dry dock at Damen Shiprepair Brest in France. The project included replacement of an approximately 80-ton stabilizer manufactured by Fouré Lagadec, requiring significant hull modifications to remove and install the equipment. Both Azipod propulsion units were dismantled for replacement of rotation bearings and other components. Two bow thrusters underwent detailed inspections and servicing, while the third was scheduled for replacement. Additional work included hull valve maintenance, classification inspections, hull cleaning, repairs, and repainting. The three-week project focused on major propulsion, maneuverability, and stabilization system maintenance rather than extensive passenger-area refurbishment. The ship returned to passenger service in Southampton on November 12.